NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

February 20 , 2023

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

February 9 , 2023

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

January 16 , 2023

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

December 27 , 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

December 5 , 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

November 10 , 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

October 26 , 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

October 10 , 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

September 26, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

September 19-21, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

September 7, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

August  25, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

August 11, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

August 1, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

July 25, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

July 14, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

July 7, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

June 29, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

June 21, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

June 8, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

June 1, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

May 10, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

April 27, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

April 14, 2022

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

April 5, 2022

Concrete: We Have placed the 8” reinforced vehicular slab where the Fire Dept. trucks will reside. This has allowed us to proceed with the final wall framing at the fire department garage. We will be continuing with the remaining concrete footings and bollards as the Spring weather allows.

Drywall/Ceilings: We will be concentrating on getting the Fire Department and Ambulance Corps. dry walled over the next few weeks. We are 100% dry walled, taped/spackled South of “C” line. Our drywall contractor is also our ceiling installer and they have been chasing the painter for ceiling grid install as the walls are primed.

Painting: Continues to follow the spackling progress in office, court/council chambers, and administration areas. We will be getting into the gymnasium area over the next few weeks to repaint the existing trusses, new ductwork and steel at the roof and attack the walls. We will also be looking to prep and start the exterior painting as weather allows.

Plumbing: Now that the shower and bathroom/turn-out rooms and decontamination shower and laundry space have been framed, the plumbing rough has been in full force over the past 2 weeks and we will be looking forward for arrival of the new fixtures, sinks, toilets, etc. over the next month. The bathrooms have all been field measured for the partitions and will be installed once manufactured.

Electrical: The electricians have been working on new light fixture and outlet install at the office and administration areas and wiring rough has been completed at the Fire Department garage. Fire alarm rough-in and devices are ongoing. The exterior site lighting has been energized and tested. We have completed the rough for all low voltage aspects to support the building. Phone, IT, security, etc. We will start to install the switches, data ports and security devices over the next few months.

Sprinkler: Starting to get into sprinkler head install in the grid, job wide. New Fire department connections have been installed at the exterior and hydrostatic testing of the system has commence and will continue over the next few weeks.

Flooring: The flooring contractor has completed all of the floor prep (outside of the gymnasium area) and vapor barrier for the eventual finishes, i.e. Carpet, VCT and LVT. Those finished floors will be installed more towards the last few weeks of the project to make sure they are not damaged. Ceramic tile at all of the bathrooms is 60% complete and will continue at the North end over the next few weeks.

HVAC: The HVAC contractor has started to install finished diffusers for conditioned air following the ceiling grid install. We will be installing the new RTU’s (roof top units and exhaust fans the week of April 11 which will allow final duct connections to the duct we have already installed on the interior of the building.

Glass and glazing: The new entry vestibule storefront glass and doors have been installed. Next step as we get further into the finishes of the interior will be transaction windows, door lights, bathroom mirrors, etc.

Roofing: We are 80% roofed in including HVAC curbs for the new RTU’s. We will be starting to finish the roof details up over the next few weeks.

Elevator: The elevator installation has begun and is 60% complete. The cab has been constructed, gear installed and protective devices, sprinkler, fire alarm, etc. are well on their way.

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

March 1, 2022

Concrete:  We have placed the new 6” slab in the new Fire Dept. garage, the next step will be to place the  8” vehicular slab where the FD trucks will be parked.  We are also prepping for the Ambulance Corps’.   The Egress stairs from the 2nd floor mezzanine South of “C” line have been installed and soon as the spring weather breaks we will be doing the balance of sidewalks and patio area at the exterior.

Drywall: 95 % of the interior walls South of A line have been framed, drywall panels have been installed and are being finish coated with tape and spackle now.  Ready for paint.

Painting:  The interior paint contractor is on site and chasing the taper/spackle crews.  They will also begin to paint the door frames that have been installed in the past week.  Exterior paint will commence once the weather breaks

Plumbing:  We have all of the Southernmost bathroom areas roughed in and ready for ceramic tile which commences this week.

Electrical:  We have started installing some interior finish lighting and have begun installing the new fixtures at the top of the exterior light poles at the parking lots.  They have also continued fire alarm wiring and getting ready for fixtures.

Sprinkler:  Have continued with rough piping for eventual ceiling installation and working on the high piping at the fire department and ambulance corps. bays.

Flooring:  The flooring contractor has been prepping the existing slab for finishes including installation of a vapor barrier which protects the eventual finished floor materials.

HVAC:  Our contractor has been working on the prep for the new roof top units which should be arriving in March.  New curb (base)  install for the units and close coordination with the roofer to keep the building weather tight through winter.

Glass and glazing:  Our contractor has installed about 75% of our exterior window frames and glass and should be completing their work over the next few weeks.

 

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE

02/01/2022 through 02-11-2022

Duct install South of C line. Gymnasium spiral duct continue install
Continue piping North at garage
Continue domestic North, gas piping at roof
Wire distribution all areas. new low voltage drops in wall
Continue framing, one side gyp and taping. Work on transaction windows
Punched window frame install East side. Caulker mobilized to site for exterior window caulking
Start curb install at roof. Controls sub on site running controls wiring.
Wire distribution all areas. new low voltage drops in wall. Gymnasium lighting feeds
Continue framing, both side gyp and taping. Finish framing court room bench hard ceiling
Working on closing in roof curbs at RTU locations

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE - WEEK OF 01-17-2022

 

Continue duct installation N of C line and 2nd floor at mezzanines. Controls electrician pulling wires for t-stats and dampers.
Continue vent, waste and domestic piping South.
Continue framing and taping South of C line.
Continue erection and detailing of stair 1.
Continue stair 2 install.
Continue one side gyp and framing South of C line..2 tapers on site.
Continue prep for inspection at South public bathroom.
Began installing new low voltage drops in wall.
Started domestic North, gas piping at roof.
Started piping North at garage.

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE - WEEK OF 12-20-2021

 

Continue duct installation and continue carrier, vent and waste piping.
Continue power and lighting distribution
Continue interior framing and roofing installation at new addition

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE 12-06-2021

 

Continue ductwork install and insulation
Continue roof installation to the North
Continue branch piping and drops, chasing the wall framing
Continue floor drain and CO's at all bathrooms
Continue framing West to East South of C line to about 5 line today SE. Leaving a pathway at South to facilitate deliveries.
Continue detailing steel interior and decking. Working on generator dunnage South.

NEW MUNICIPAL COMPLEX CONSTRUCTION UPDATE 11-19-2021

 

Exterior landscaping and hardscaping have been ongoing with new curbing, lawn areas and ground cover installed. Twenty five foot Norway Spruce tree planted at south east corner of the building for the Holiday Tree Lighting Ceremony on Friday, November 26th. Protective bollards and new sidewalks have been installed at the eventual new entrance to the different program areas of the space.

 

The ironworkers have completed the steel “skeleton” of the new addition for the Fire Department (FD) and Ambulance Corps bays at the north side. We will continue to install roof decking and exterior walls at the addition over the next weeks. In addition, the interior second floor mezzanine is installed with the structural members and decking on that is ongoing as of 11-17-2021.

 

The concrete footings and infills are 80% complete and will be completing in the next few weeks. Our next large concrete placement will be for the new slab at the FD bays and Ambulance Corps bays, north end.

 

The masons have completed the elevator shaft and brought the top of wall to finish elevation today (11-17-2021). Roofers will quickly follow to make the penetration through the roof water-tight and get ready for the new roofing.

 

The carpenters have been working on the second floor mezzanine area floor decking and have started framing walls at the first floor to develop the municipal office areas, the courtroom/council chambers area, the public bathroom spaces and main entries.

 

The plumbers are 85% complete with underground sanitary pipe installation and have started to work on domestic water distribution to the bathrooms, snack bar, FD decontamination shower and exterior wall hydrant locations.

 

The HVAC contractor has started to fabricate duct for conditioned air once the new rooftop mounted air-handling units (AHU’s) arrive to the site. We should have a good deal of ductwork installed for conditioned air distribution by the time they arrive.

 

The electricians have been working on power and lighting distribution wiring for the new space and are working on all aspects of the electrical systems to power and light the new space.

 

Waterproofing has commenced and is approximately 70% complete with only the west side to repair and re-caulk the existing joints between pre-cast panels.

 

The sprinkler contractor has had a presence on site and has relocated sprinkler lines as needed for the base construction activities and will become more involved as the project progresses.

 

New municipal complex update #2 -9/14/21

The work continues at our new building as the elevator pit is in as well as the cut out for the windows are complete.

Concrete work continues and in a short time we expect to have various trade groups (plumber, electrical, etc.) start their work.

It’s exciting to share the progress with you as the various components of the building start to take shape.

In July 2021, the Township began its journey of providing a municipal complex for our residents.

We will be posting pictures sharing the progress with you as we take an empty building and transform it into a civic center, Hook and Ladder Fire House, an Ambulance Corps area and municipal offices.

This page will be updated as construction moves ahead.